The Water Authority of Fiji has announced several significant milestones in the ongoing repair and restoration efforts following the recent pipe damage along Savura Road.
Welding works on the 600 main were successfully completed yesterday, marking a crucial step towards the full reinstatement of water services in the affected areas.
Following the completion of welding, backfilling and pipe stabilization works are currently underway, ensuring the structural integrity of the repaired pipeline.
WAF also reports that the damaged raw water line is now online, facilitating the resumption of water supply production at the Tamavua treatment plant.
As the restoration efforts progress, water services will gradually be restored to affected areas.
The Water Authority of Fiji reassures residents that every effort is being made to expedite the restoration of water services.
60 year old man dies in tragic road accident
Apr 06, 2025, 12:03 PM
100 families complete pre-departure training for PALM scheme in Australia
Apr 05, 2025, 02:45 PM
5,000+ dengue cases reported; Ministry urges vigilance
Apr 05, 2025, 02:37 PM
Two arrested in Suva for alleged drug possession
Apr 04, 2025, 04:31 PM
President Ratu Naiqama visits Namoli village and reflects on personal...
Apr 04, 2025, 01:02 PM
60 year old man dies in tragic road accident
Apr 06, 2025, 12:03 PM
100 families complete pre-departure training for PALM scheme in Australia
Apr 05, 2025, 02:45 PM
5,000+ dengue cases reported; Ministry urges vigilance
Apr 05, 2025, 02:37 PM
Two arrested in Suva for alleged drug possession
Apr 04, 2025, 04:31 PM
President Ratu Naiqama visits Namoli village and reflects on personal...
Apr 04, 2025, 01:02 PM